Installing an insulated raft foundation involves several coordinated stages: preparing the ground, positioning services, assembling the insulation system, installing the specified membranes and reinforcement, and placing the concrete.
For self-builders and contractors, understanding that sequence helps with organising deliveries, agreeing responsibilities and preparing for the concrete pour.
This guide explains the overall ISOQUICK installation process. The current installation instructions, project assembly plan and engineer's design provide the detailed requirements for each site.
1. Agree the design and responsibilities
Before installation, the project team needs to establish whether the proposed foundation is suitable for the ground conditions and the building it will support.
The structural engineer must design the concrete slab and reinforcement for the project. Ground conditions, building loads and the proposed construction above the raft need to inform those decisions.
ISOQUICK's role includes advice on its system layout and relevant construction details. That support works alongside the appointed structural engineer's responsibilities.
Before booking site work, agree who is responsible for:
- Ground preparation and setting-out.
- Drainage and service installation.
- ISOQUICK assembly.
- Membranes and penetration seals.
- Reinforcement and concrete.
- Inspections and records before work is covered.
For design decisions at walls, thresholds and services, see our guide to five insulated raft foundation junctions.
2. Prepare the ground and sub-base
The insulation system needs a prepared supporting base. The published Kiwa documentation describes a free-draining sub-base constructed to the engineer's specification, with fill placed and compacted in layers. Drains and ducts follow the compacted sub-base, before the final blinding layer is completed.
The blinding provides the flat, level surface for assembling the system. Ground preparation therefore needs completing before the insulation installation begins.
Use Installation Guide Part 1: Groundworks to coordinate this stage with the groundworks contractor.
3. Confirm drainage and service positions
Check the position of each pipe and duct against the coordinated drawings before assembling the insulation around it. Compare the service layout with the room layout: do drainage connections align with the intended sanitary fittings, and are incoming services emerging in the agreed positions?
Changes should be resolved with the relevant designer before the concrete pour. Where services pass through ISOQUICK components, the boards are cut to fit around them. The insulation opening and membrane penetration need their respective specified seals; sealing a gap in the EPS does not replace the membrane detail.
4. Assemble the perimeter and internal insulation
ISOQUICK is supplied with a project assembly plan identifying corners and non-standard components.
Installation starts with the perimeter edge modules. Their dovetail connections join the components together, while alignment is checked against the setting-out. The internal base and top boards then fill the enclosed area. The layers use an offset arrangement so joints overlap, with checks during installation to maintain alignment and a close fit.
Delivery access and a suitable storage area should be arranged beforehand. Although the components are lightweight, they are bulky and require suitable precautions for handling, wind and cold weather.
5. Install the specified membranes and reinforcement
The standard sequence in ISOQUICK's UK installation guide places the damp-proof membrane over the assembled insulation before reinforcement.
Corners and penetrations need careful detailing, with sufficient membrane retained at the perimeter. Any radon or other ground-gas protection must follow the project's specified protection strategy.
Reinforcement is installed to the structural engineer's design, using suitable supports to maintain its required position and protect the membrane. If underfloor heating is proposed, agree its position within the floor build-up and its installation stage before programming the pour. See the focused guide to coordinating underfloor heating with an insulated raft.
6. Complete the pre-pour checks
Allow a clear checking stage before concrete arrives. Use the approved drawings and installation instructions to confirm:
- Dimensions, setting-out and levels.
- Insulation assembly and component condition.
- Drainage and service positions.
- Membrane continuity and penetration seals.
- Reinforcement position and cover.
- Thresholds, openings and bespoke edge details.
- Any agreed inspections before covering the work.
Record the checks and resolve outstanding questions with the responsible designer or installer.
7. Place the concrete and plan the next stage
The concrete specification comes from the engineer. ISOQUICK's guide describes placing the slab in one continuous operation and notes that bespoke details may need additional form support identified on the assembly plan.
The guide also requires protection of exposed EPS edges before backfilling. Agree finishing, curing, protection and the timing of subsequent loading with the responsible construction team. Completing the pour and being ready for the next trade are separate programme decisions.
How long does insulated raft installation take?
There is no reliable universal duration for every site. Separate the programme into groundworks, service installation, insulation assembly, membrane and reinforcement work, concrete placement, and the period before subsequent construction.
Project size, complexity, site conditions and reinforcement design all affect the programme. Request a project-specific sequence when arranging installation support.